At Onyx​ Incorporated, direct materials are added at the beginning of the process and conversions costs are uniformly applied. Other details​ include:
WIP beginning​ (70% for​ conversion)
​15,200 units
Units started
​150,000 units
Units completed and transferred out
​120,000 units
WIP ending​ (50% for​ conversion)
​45,200 units
Beginning WIP direct materials
​$52,500
Beginning WIP conversion costs
​$25,200
Costs of materials added
​$443,100
Costs of conversion added
​$260,000
What is the total cost of units remaining in ending​ WIP?
-----------