QuickHelper

(10)

$20/per page/

About QuickHelper

Levels Tought:
Elementary,High School,College,University,PHD

Expertise:
Accounting,Applied Sciences See all
Accounting,Applied Sciences,Business & Finance,Chemistry,Engineering,Health & Medical Hide all
Teaching Since: May 2017
Last Sign in: 356 Weeks Ago, 2 Days Ago
Questions Answered: 20103
Tutorials Posted: 20155

Education

  • MBA, PHD
    Phoniex
    Jul-2007 - Jun-2012

Experience

  • Corportae Manager
    ChevronTexaco Corporation
    Feb-2009 - Nov-2016

Category > Accounting Posted 14 May 2017 My Price 13.00

Sales and Operations Planning

Question description

 

The forecasting department, traditionally reporting to the sale manager, has historically seen a forecast accuracy of about 60%, and this in turn causes problems for the following departments:

  • Purchasing: What should we buy and how much?
  • Production: What should we really build?
  • Inventory management: We keep building the wrong thing.

The sales manager asked you to write her a memo, specifically addressing the following:

  • How could you suggest that your new system would achieve any better levels of forecast accuracy?
  • Why is forecast accuracy itself not as important under traditional methods?
  • Create a chart or timeline that includes all of the following:
    • Which purchase orders have to be placed, and when
    • When manufacturing needs to begin, to have products delivered to a customer
    • Approximate dates for all of the following:
      • When the product must be shipped to meet the customer's due date
      • When the application of the cover and packaging must take place to meet the customer's due date
      • When the manufacturing of the widget must begin and end
      • When the raw material for the widget must be ordered
      • When the plastic cover must be ordered
      • When the cardboard box must be ordered
    • Includes notes explain your timing calculation
    • Assumes all of the following conditions:
      • The factory has two departments: manufacturing and packaging
      • Product X consists of 3 components
      • a widget manufactured in the factory with a total manufacturing lead time of 1 week
      • a plastic cover purchased from vendor A with a procurement lead time of 3 weeks
      • a cardboard shipping box purchased from vendor B with a procurement lead time of 4 weeks
      • The widget itself is made from steel (whose lead time from vendor C is 4 weeks).
      • It takes 1 day for the cover to be applied to the product and for the product to be inserted in the box in the packaging department.
      • The shipping time to this customer is in 3 weeks, and you do not want it to be late or early.
      • Assume you received the customer order on 1/1/20XX.
      • Ignore any holidays
      • Assume a 5-day work week
      • The customer requires the product to arrive at his location on 3/31/2011

Answers

(10)
Status NEW Posted 14 May 2017 07:05 PM My Price 13.00

Hel-----------lo -----------Sir-----------/Ma-----------dam----------- T-----------han-----------k Y-----------ou -----------for----------- us-----------ing----------- ou-----------r w-----------ebs-----------ite----------- an-----------d a-----------cqu-----------isi-----------tio-----------n o-----------f m-----------y p-----------ost-----------ed -----------sol-----------uti-----------on.----------- Pl-----------eas-----------e p-----------ing----------- me----------- on----------- ch-----------at -----------I a-----------m o-----------nli-----------ne -----------or -----------inb-----------ox -----------me -----------a m-----------ess-----------age----------- I -----------wil-----------l

Not Rated(0)