QuickHelper

(10)

$20/per page/

About QuickHelper

Levels Tought:
Elementary,High School,College,University,PHD

Expertise:
Accounting,Applied Sciences See all
Accounting,Applied Sciences,Business & Finance,Chemistry,Engineering,Health & Medical Hide all
Teaching Since: May 2017
Last Sign in: 352 Weeks Ago, 5 Days Ago
Questions Answered: 20103
Tutorials Posted: 20155

Education

  • MBA, PHD
    Phoniex
    Jul-2007 - Jun-2012

Experience

  • Corportae Manager
    ChevronTexaco Corporation
    Feb-2009 - Nov-2016

Category > Management Posted 23 Oct 2017 My Price 10.00

Went Hang Investment Co

Went Hang Investment Co. Ltd. ("Went Hang") is a Hong Kong corporation with its principal place of business in Hong Kong. C.J. International Trading Inc. ("C.J. Int'l") is a New York corporation with its principal place of business in New York.

Went Hang is an importer and distributor of various raw materials. On approximately Feb. 16, through its agent Success Universal Limited, Went Hang entered into a contract to purchase 800 metric tons of polyester chips from C.J. Int'l for $1.92 per kilogram, C&F Hong Kong, or a total of $1,536,000.00.

The contract provided that the time of shipment for the first 400 metric tons was to be between February and May. The second 400 metric tons was to be shipped in July. The goods were to be shipped from Mexico (where they were made) to Hong Kong. The contract was silent as to the route to be taken, nor did it contain a "time is of essence" clause or any provision related to arrival or delivery.

Prior to the arrival of the goods in Hong Kong, C.J. Int'l requested Went Hang's payment for the first lot of goods. Unbeknownst to Went Hang, C.J. Int'l had transshipped the goods through Rotterdam, and that fact meant that the shipment would not arrive as quickly as Went Hang thought. The fact that the goods were being trans-shipped through Rotterdam was not apparent from the documents presented for payment. On approximately May 6, Went Hang paid C.J. Int'l for the shipment of the first lot of polyester chips.

Because the chips were transshipped through Rotterdam, the first shipment did not arrive in Hong Kong until June 23. Went Hang believes that C.J. Int'l knew that the trans-shipment would delay arrival, and that C.J. Int'l had concealed that fact from Went Hang. 

On July 1, Went Hang's attorney in Hong Kong notified C.J. Int'l that Weng Hang would not pay for the second lot of goods unless C.J. Int'l promised not to trans-ship through Europe. C.J. Int'l declined to so promised, and C.J. Int'l did not make the second shipment.

Went Hang sued C.J. Int'l for in New York for breach of contract. C.J. Int'l counterclaimed for anticipatory breach.

What result would you expect? Please support your reasoning. 

Answers

(10)
Status NEW Posted 23 Oct 2017 02:10 PM My Price 10.00

Hel-----------lo -----------Sir-----------/Ma-----------dam----------- T-----------han-----------k Y-----------ou -----------for----------- us-----------ing----------- ou-----------r w-----------ebs-----------ite----------- an-----------d a-----------cqu-----------isi-----------tio-----------n o-----------f m-----------y p-----------ost-----------ed -----------sol-----------uti-----------on.----------- Pl-----------eas-----------e p-----------ing----------- me----------- on----------- ch-----------at -----------I a-----------m o-----------nli-----------ne -----------or -----------inb-----------ox -----------me -----------a m-----------ess-----------age----------- I -----------wil-----------l