Question 4. 4. (TCO C) A project to remodel a garage has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)
ActivityDurationPredecessors
A4 months---
B3 months---
C3 months---
D5 monthsC
E3 monthsA, B
F3 monthsB, C
G3 monthsE, F
H4 monthsD, F
I5 monthsG
J2 monthsH
-----------