Table Manufacturing Company produce one style of tables
the following data pertains to producing one table
Planned production per month
Units (one table) 100
Piece of wood (M) 20
Estimated M price $30
Actual production
Quantity purchased (QP) $18
Actual Price (AP) $34
The calculated material price variance is?
-----------