Use the table “Manufacturing Capacity Utilization” to answer the questions below.
|
Manufacturing Capacity Utilization In Percentages |
|||
|
Day |
Utilization |
Day |
Utilization |
|
1 |
82.5 |
9 |
78.8 |
|
2 |
81.3 |
10 |
78.7 |
|
3 |
81.3 |
11 |
78.4 |
|
4 |
79.0 |
12 |
80.0 |
|
5 |
76.6 |
13 |
80.7 |
|
6 |
78.0 |
14 |
80.7 |
|
7 |
78.4 |
15 |
80.8 |
|
8 |
78.0 |
Part (a) What is the project manufacturing capacity utilization for Day 16 using a three day moving average?
Part (b) What is the project manufacturing capacity utilization for Day 16 using a six day moving average?
Part (c) Use the mean absolute deviation (MAD) and mean square error (MSE) to determine which average provides the better forecast
Hel-----------lo -----------Sir-----------/Ma-----------dam----------- T-----------han-----------k Y-----------ou -----------for----------- us-----------ing----------- ou-----------r w-----------ebs-----------ite----------- an-----------d a-----------cqu-----------isi-----------tio-----------n o-----------f m-----------y p-----------ost-----------ed -----------sol-----------uti-----------on.----------- Pl-----------eas-----------e p-----------ing----------- me----------- on----------- ch-----------at -----------I a-----------m o-----------nli-----------ne -----------or -----------inb-----------ox -----------me -----------a m-----------ess-----------age----------- I -----------wil-----------l