Edwards Corporation is working on its direct labor budget for the next two months. Each unit of output requires 0.7 direct labor-hours. The direct labor rate is $8.50 per direct labor-hour. The production budget calls for producing 4,800 units in June and 5,300 units in July.
Â
Construct the direct labor budget for the next two months, assuming that the direct labor work force is fully adjusted to the total direct labor-hours needed each month.
-----------