H55 Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows:
Â
Materials (0.90 yards × $12.50)$11.25Direct labor (1.20 hours × $13.70)$16.44
During May, the company produced 3,390 band hats; 3,970 yards of material were purchased for $40,097, and 3,020 yards of material were used in production. Also during May, 4,660 direct labor hours were worked at a cost of $55,920. Calculate material price and quantity variances and labor rate and efficiency variances. Indicate whether the variances are favorable or unfavorable.
Â
Material Price Variance?
Material Quantity Variance?
Labor Rate Variance?
Labor Efficiency Variance?
-----------