SuperTutor

(15)

$15/per page/Negotiable

About SuperTutor

Levels Tought:
Elementary,Middle School,High School,College,University,PHD

Expertise:
Accounting,Business & Finance See all
Accounting,Business & Finance,Economics,Engineering,HR Management,Math Hide all
Teaching Since: Apr 2017
Last Sign in: 235 Weeks Ago, 2 Days Ago
Questions Answered: 12843
Tutorials Posted: 12834

Education

  • MBA, Ph.D in Management
    Harvard university
    Feb-1997 - Aug-2003

Experience

  • Professor
    Strayer University
    Jan-2007 - Present

Category > Management Posted 02 May 2017 My Price 15.00

project management plan

Question 1
1. Which of the following statements accurately describes a project management plan?
A formal document that defines how the project is initiated and planned.
A formal document that defines how the project is executed, monitored and
controlled.
A formal document that defines how the project is terminated and closed.
A formal document that is the legal contract for the project. Question 2
1. Which of the following statements accurately describes the approach that project
managers should take to develop relationships with key stakeholders?
The project manager should defer building relationships with external stakeholders
until after the core team is on sound footing.
It is better to ignore an unhappy stakeholder than to let him or her disrupt a project.
Project managers should seek to understand what motivates each stakeholder.
Stakeholders should be involved at the completion of the project. Question 3
1. Which of the following responses most accurately depicts the correct sequence of
activities in the strategic planning process?
strategic objectives - strategic analysis - guiding principles - flow-down objectives
guiding principles - strategic analysis - strategic objectives - flow-down objectives
strategic analysis - guiding principles - strategic objectives - flow-down objectives
guiding principles - strategic objectives - flow-down objectives - strategic analysis Question 4
1. Which of the following items best depicts the scope definition process?
It begins by clarifying project objectives and culminates in a baseline scope
statement.
It begins by establishing a scope baseline and culminates in scope verification.
It begins with user requirements and culminates in a product specification. It begins with identifying resource levels and a timetable. Question 5
1. Which of the following items best describes a project Work Breakdown Structure
(WBS)?
An organizational chart depicting who will perform project work.
A schedule depicting when project work will be performed.
A framework that identifies project deliverables.
A budget for project costs. Question 6
1. A deliverable at the lowest level of each branch of a work breakdown structure is known
as:
a work element.
a work package.
a work unit.
a work cell. Question 7
1. A scheduled activity that determines when a logical successor activity can begin and end
is known as:
a catalyst activity.
a predecessor activity.
a leader activity.
a starter activity. Question 8
1. The total number of work periods (not including holidays or other non-work time)
required to complete a scheduled activity is known as:
effort.
elapsed time. duration.
scheduled time. Question 9
1. Which of the following statements correctly describes the critical path?
It is the shortest sequence of activities through the project network.
It determines the latest possible end date of the project.
It consists only of activities with zero slack.
It consists of the most important activities in the project. Question 10 Figure 7-1 Consider the Assembly Project depicted in Figure 7-1. Based on the information
provided, what is the early start date for activity D - “Attach Modules 1 & 2”? Day 0. Day 3. Day 4. Day 5. Question 11 Figure 7-1 Consider the Assembly Project depicted in Figure 7-1. Based on the
information provided what is the amount of slack in Activity B – “Assemble Module 1”?
0 days. 1 day. 2 days. not enough information to determine. Question 12
1. Projects often include indirect costs that are not associated directly with one specific
project. Which of the following items are most typically considered to be indirect costs?
Costs associated with material, travel and purchased parts.
The cost of labor provided by project team members, consultants and
subcontractors.
Executive salaries, utilities and insurance.
Specialized equipment rented for a particular task. Question 13
1. Which of the following terms best describes the amount of funds needed above the
estimate to reduce the risk of overruns?
Contingency reserve.
Insurance funds.
Project padding.
Discretionary funds. Question 14
1. The approved time-phased budget against which project execution is compared and
deviations are measured for management control is known as:
a measurement baseline.
a cost baseline.
a control standard.
the PERT/CPM chart. Question 15
1. Which of the following describes the activities appropriately performed by the project
team during qualitative risk analysis?
Team members assess the probability of occurrence and severity of impact for
identified risks.
Team members develop contingency plans for even minor risks to avoid adverse
impacts to project objectives. Team members identify potential risk events.
Team members consult with stakeholders concerning responsibilities. Question 16 ID Risk Event Likelihood Severity A Project requires new technology and support structure Medium Low B Web infrastructure lacks sufficient transaction capacity Medium High C IS resources are spread too thin High High D The intranet site suffers a security breach Low High 1. Figure 10-1 Excerpt from Internet Project Risk Register 2. Consider the excerpt of the Internet Project risk register presented in Figure 10-1. Which of the following
risk events should receive the highest priority for the development of risk responses? A - project requires new technology and support structure.
B - web infrastructure lacks sufficient transaction capacity
C - IS resources are spread too thin
D - The intranet site suffers a security breach Question 17
1. One useful method of process improvement involves consideration of how another
organization performs a process with an eye toward determining how to improve your
own performance. This method is known as: comparative improvement.
benchmarking.
variance analysis.
peer review. Question 18
1. Which of the following serves as an important guideline concerning project inspections?
Inspect after critical or expensive processes to make sure the inputs are good.
Inspect prior to key work handoff points.
Inspect at milestones identified in the project schedule.
Inspect only as a last resort. Question 19
1. A project team attempting to complete the administrative closure of a project should
review which of the following to ensure the customers are satisfied that all required work
was accomplished?
The project charter.
The scope verification.
The communication plan.
The stakeholder sign-off. Question 20
1. The Budget at Completion (BAC) is the sum of all budgeted values established for the
work to be performed on a project. As such it is equivalent to:
the total planned value of the project.
the total earned value of the project.
the total actual cost of the project.
the total amount of resources remaining at the end of the project.

 

Answers

(15)
Status NEW Posted 02 May 2017 07:05 AM My Price 15.00

-----------

Attachments

file 1493708560-Solutions file.docx preview (56 words )
S-----------olu-----------tio-----------ns -----------fil-----------e -----------Hel-----------lo -----------Sir-----------/Ma-----------dam----------- T-----------han-----------k y-----------ou -----------for----------- yo-----------ur -----------int-----------ere-----------st -----------and----------- bu-----------yin-----------g m-----------y p-----------ost-----------ed -----------sol-----------uti-----------on.----------- Pl-----------eas-----------e p-----------ing----------- me----------- on----------- ch-----------at -----------I a-----------m o-----------nli-----------ne -----------or -----------inb-----------ox -----------me -----------a m-----------ess-----------age----------- I -----------wil-----------l b-----------e q-----------uic-----------kly----------- on-----------lin-----------e a-----------nd -----------giv-----------e y-----------ou -----------exa-----------ct -----------fil-----------e a-----------nd -----------the----------- sa-----------me -----------fil-----------e i-----------s a-----------lso----------- se-----------nt -----------to -----------you-----------r e-----------mai-----------l t-----------hat----------- is----------- re-----------gis-----------ter-----------ed -----------on-----------th-----------is -----------web-----------sit-----------e. ----------- H-----------YPE-----------RLI-----------NK -----------&qu-----------ot;-----------htt-----------p:/-----------/wo-----------rkb-----------ank-----------247-----------.co-----------m/&-----------quo-----------t; -----------\t -----------&qu-----------ot;-----------_bl-----------ank-----------&qu-----------ot;----------- -----------Tha-----------nk -----------you----------- -----------
Not Rated(0)