Pier Corp. has an expected monthly capacity of 9,000 units but only 5,700 units were produced and 6,000 direct labor hours were used during August 2010 due to a flood in the manufacturing facility. Actual variable overhead for August was $48,165 and actual fixed overhead was $140,220.
Standard cost data follow:
Standard Cost per Unit
(One Unit Takes One Labor Hour)
Direct material …………………..$9.00
Direct labor …………………….15.00
Variable overhead ……………….. 8.00
Fixed overhead …………………16.00
Total …………………………… $48.00
a. Compute and compare the actual overhead cost per unit with the expected overhead cost per unit.
b. Calculate overhead variances using the four-variance method.
c. Explain why the volume variance is so large.
Hel-----------lo -----------Sir-----------/Ma-----------dam-----------Tha-----------nk -----------You----------- fo-----------r u-----------sin-----------g o-----------ur -----------web-----------sit-----------e a-----------nd -----------and----------- ac-----------qui-----------sit-----------ion----------- of----------- my----------- po-----------ste-----------d s-----------olu-----------tio-----------n.P-----------lea-----------se -----------pin-----------g m-----------e o-----------n c-----------hat----------- I -----------am -----------onl-----------ine----------- or----------- in-----------box----------- me----------- a -----------mes-----------sag-----------e I----------- wi-----------ll