E18-3Â Â Â Â Â Percentage of Completion The King Construction Company began work on a contract in 2007. The contract price is
$4,000,000, and the company uses the percentage-of-completion method. Other information relating to the contract is as follows:
|
Costs incurred during the year |
$ Â 800,000 |
|
Estimated costs to complete, December 31 |
2,400,000 |
|
Billings during the year |
600,000 |
|
Collections during the year Required |
400,000 |
1.     How much gross profit or loss does King recognize in 2007?
2.     Prepare the appropriate sections of the 2007 income statement and ending balance sheet.
Hel-----------lo -----------Sir-----------/Ma-----------dam-----------Tha-----------nk -----------You----------- fo-----------r u-----------sin-----------g o-----------ur -----------web-----------sit-----------e a-----------nd -----------and----------- ac-----------qui-----------sit-----------ion----------- of----------- my----------- po-----------ste-----------d s-----------olu-----------tio-----------n.P-----------lea-----------se -----------pin-----------g m-----------e o-----------n c-----------hat----------- I -----------am -----------onl-----------ine----------- or----------- in-----------box----------- me----------- a -----------mes-----------sag-----------e I----------- wi-----------ll