Cornerstone Exercise 11-29Â Â Â Â Â Â Â Â Â Â Â Â Activity-Based Performance Report
Jarend Company produced 40,000 units last year. The information on the actual costs and budg- eted costs at actual production of four activities is provided below.
|
Activity |
Actual Cost |
Budgeted Cost for Actual Production |
|
Maintenance |
$158,300 |
$158,000 |
|
Machining |
205,400 |
205,000 |
|
Setting up |
106,700 |
105,000 |
|
Purchasing |
158,800 |
159,000 |
Required:
Prepare an activity-based performance report for the four activities for the past  year.