Alpha Geek

(8)

$10/per page/Negotiable

About Alpha Geek

Levels Tought:
University

Expertise:
Accounting,Algebra See all
Accounting,Algebra,Architecture and Design,Art & Design,Biology,Business & Finance,Calculus,Chemistry,Communications,Computer Science,Environmental science,Essay writing,Programming,Social Science,Statistics Hide all
Teaching Since: Apr 2017
Last Sign in: 442 Weeks Ago, 4 Days Ago
Questions Answered: 9562
Tutorials Posted: 9559

Education

  • bachelor in business administration
    Polytechnic State University Sanluis
    Jan-2006 - Nov-2010

  • CPA
    Polytechnic State University
    Jan-2012 - Nov-2016

Experience

  • Professor
    Harvard Square Academy (HS2)
    Mar-2012 - Present

Category > Accounting Posted 10 May 2017 My Price 12.00

Construct the project network

 

  1. The following table provides the information necessary to construct a project network and proj- ect crash data:

 

Activity Time Activity (weeks) Cost

 

Activity

( i, j )

ActivityPredecessor

Normal

Crash

 

Normal

Crash

a

(1, 2)

—

16

8

 

$2,000

$4,400

b

(1, 3)

—

14

9

 

1,000

1,800

c

(2, 4)

a

8

6

 

500

700

d

(2, 5)

a

5

4

 

600

1,300

e

(3, 5)

b

4

2

 

1,500

3,000

f

(3, 6)

b

6

4

 

800

1,600

g

(4, 6)

c

10

7

 

3,000

4,500

h

(5, 6)

d, e

15

10

 

5,000

8,000

 

  1. Construct the project network.

  2. Manually crash the network to 28 weeks.

  3. Formulate the general linear programming model for this network.

  4. Formulate the linear programming crashing model that would crash this model by the maxi- mum amount.

 

 

 

 
 