Vikram Ltd. produces 4 products using 3 different
machines. Machine capacity is limited to 3,000 hours for each machine. The
following information is available for February, 2009:
Products A B C D
Contribution (Sales-direct material)`
Machine Hours Required/ Unit:
1,500 1,200 1,000 600
Machine 1 10 6 2 1
Machine 2 10 9 3 1.5
Machine 3 10 3 1 0.5
Estimated Demand (units) 200 200 200 200
From the above information you are required to identify the bottleneck
activity and allocate the machine time.
Hel-----------lo -----------Sir-----------/Ma-----------dam-----------Tha-----------nk -----------You----------- fo-----------r u-----------sin-----------g o-----------ur -----------web-----------sit-----------e a-----------nd -----------and----------- ac-----------qui-----------sit-----------ion----------- of----------- my----------- po-----------ste-----------d s-----------olu-----------tio-----------n.P-----------lea-----------se -----------pin-----------g m-----------e o-----------n c-----------hat----------- I -----------am -----------onl-----------ine----------- or----------- in-----------box----------- me----------- a -----------mes-----------sag-----------e I----------- wi-----------ll