1. What is the minimum cost of crashing the following project by 3 days?
Â
Â
Â
|
Activity |
Normal Time (days) |
Crash Time (days) |
Normal Cost |
Crash Cost |
Immediate Predecessor(s) |
|
A |
6 |
5 |
$ 900 |
$1,000 |
— |
|
B |
8 |
6 |
300 |
400 |
— |
|
C |
4 |
3 |
500 |
600 |
— |
|
D |
5 |
3 |
900 |
1,200 |
A, B |
|
E |
8 |
5 |
1,000 |
1,600 |
 |
Hel-----------lo -----------Sir-----------/Ma-----------dam-----------Tha-----------nk -----------You----------- fo-----------r u-----------sin-----------g o-----------ur -----------web-----------sit-----------e a-----------nd -----------acq-----------uis-----------iti-----------on -----------of -----------my -----------pos-----------ted----------- so-----------lut-----------ion-----------.Pl-----------eas-----------e p-----------ing----------- me----------- on-----------cha-----------t I----------- am----------- on-----------lin-----------e o-----------r i-----------nbo-----------x m-----------e a----------- me-----------ssa-----------ge -----------I w-----------ill----------- be-----------