7.             Embassy Club Condominium, located on the west coast of Florida, is undertaking a sum- mer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times:
Â
Â
Â
Â
Â
|
 Activity |
Immediate Predecessor |
 Time |
|
A |
— |
3 |
|
B |
— |
1 |
|
C |
— |
2 |
|
D |
A, B, C |
4 |
|
E |
C, D |
5 |
|
F |
A |
3 |
|
G |
D, F |
6 |
|
H |
E |
4 |
Â
Â
Â
a.            Â
Draw a project network.
Â
b.             What are the critical activities?
Â
c.              What activity has the most slack time?
Â
d.             Will the project be completed by September 1?
Â
Hel-----------lo -----------Sir-----------/Ma-----------dam-----------Tha-----------nk -----------You----------- fo-----------r u-----------sin-----------g o-----------ur -----------web-----------sit-----------e a-----------nd -----------acq-----------uis-----------iti-----------on -----------of -----------my -----------pos-----------ted----------- so-----------lut-----------ion-----------.Pl-----------eas-----------e p-----------ing----------- me----------- on-----------cha-----------t I----------- am----------- on-----------lin-----------e o-----------r i-----------nbo-----------x m-----------e a----------- me-----------ssa-----------ge -----------I w-----------ill----------- be-----------