The following is a table of activities associated with a project at Rafay? Ishfaq's software firm in? Chicago, their? durations, what activities each must precede and the crash cost to reduce duration per? week:
|
Activity |
Duration? (weeks) |
Precedes |
Crash? Cost/Week |
|
A? (start) |
3 |
?B, C |
$380 |
|
B |
2 |
E |
$120 |
|
C |
6 |
F |
$220 |
|
E |
2 |
F |
$160 |
|
F? (end) |
2 |
— |
$400 |
Suppose that Rafay is only given 8 weeks? (instead of 11?)
to complete the project. By how many weeks should each activity be crashed in order to meet the? deadline? Assume that you can crash an activity down to 0 weeks duration.
|
Activity |
Each Activity Should be Reduced BY ?(weeks) |
|
A |
0 ?week(s) |
|
B |
0 ?week(s) |
Can you do A-F please!
Hel-----------lo -----------Sir-----------/Ma-----------dam-----------Tha-----------nk -----------You----------- fo-----------r u-----------sin-----------g o-----------ur -----------web-----------sit-----------e a-----------nd -----------acq-----------uis-----------iti-----------on -----------of -----------my -----------pos-----------ted----------- so-----------lut-----------ion-----------.Pl-----------eas-----------e p-----------ing----------- me----------- on-----------cha-----------t I----------- am----------- on-----------lin-----------e o-----------r i-----------nbo-----------x m-----------e a----------- me-----------ssa-----------ge -----------I w-----------ill----------- be-----------