Maurice Tutor

(5)

$15/per page/Negotiable

About Maurice Tutor

Levels Tought:
Elementary,Middle School,High School,College,University,PHD

Expertise:
Algebra,Applied Sciences See all
Algebra,Applied Sciences,Biology,Calculus,Chemistry,Economics,English,Essay writing,Geography,Geology,Health & Medical,Physics,Science Hide all
Teaching Since: May 2017
Last Sign in: 437 Weeks Ago
Questions Answered: 66690
Tutorials Posted: 66688

Education

  • MCS,PHD
    Argosy University/ Phoniex University/
    Nov-2005 - Oct-2011

Experience

  • Professor
    Phoniex University
    Oct-2001 - Nov-2016

Category > Management Posted 20 Feb 2018 My Price 8.00

ahead or behind schedule

AmyA????1s project is to produce 300 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely cost constrained. Performance data for the project at the end of week three is presented below:

190 total units were planned to be produced

200 units have actually been produced

The financial manager reported that the business had actually spent $15,000 on the project by the end of week three.

Answer the following questions; show all work:

1.Quantify cost variance. Is the project ahead or behind budget?

2. Quantify schedule variance. Is the project ahead or behind schedule?

3. Quantify cost performance efficiency. Is the project performing better or worse than planned?

4. Quantify schedule performance efficiency. Is the project performing better or worse than planned?

5. What is the forecast of project cost at completion assuming current cost performance efficiency remains the same? How much budget variance is expected at completion?

6. What is the forecast of funding needed to complete the project (from this point forward)?

7. What cost performance efficiency would be required for the remainder of the project to complete the project within the original budget?

8. As the project financial manager, what recommendations would you make?

Answers

(5)
Status NEW Posted 20 Feb 2018 06:02 PM My Price 8.00

Hel-----------lo -----------Sir-----------/Ma-----------dam-----------Tha-----------nk -----------You----------- fo-----------r u-----------sin-----------g o-----------ur -----------web-----------sit-----------e a-----------nd -----------acq-----------uis-----------iti-----------on -----------of -----------my -----------pos-----------ted----------- so-----------lut-----------ion-----------.Pl-----------eas-----------e p-----------ing----------- me----------- on-----------cha-----------t I----------- am----------- on-----------lin-----------e o-----------r i-----------nbo-----------x m-----------e a----------- me-----------ssa-----------ge -----------I w-----------ill----------- be-----------