Consider the data in the table below. Assume that your project consists only of these three activities. Your estimate at completion is $4,400.00. This means you are calculating your EAC by using which of the followingformulas?
|
Activity |
% Complete |
PV |
EV |
AC |
|
1 |
100 |
2,000 |
2,000 |
2,200 |
|
B |
50 |
1,000 |
500 |
700 |
|
C |
0 |
1,000 |
0 |
0 |
a. EAC = AC/EV × BAC
b. EAC = AC/EV × [work completed and in progress] + [actual (or revised) cost of work packages that have not started]
c. EAC = [Actual to date] + [all remaining work to be done at the planned cost including remaining work in progress]
d. EAC =% complete × BAC
Hel-----------lo -----------Sir-----------/Ma-----------dam-----------Tha-----------nk -----------You----------- fo-----------r u-----------sin-----------g o-----------ur -----------web-----------sit-----------e a-----------nd -----------acq-----------uis-----------iti-----------on -----------of -----------my -----------pos-----------ted----------- so-----------lut-----------ion-----------.Pl-----------eas-----------e p-----------ing----------- me----------- on-----------cha-----------t I----------- am----------- on-----------lin-----------e o-----------r i-----------nbo-----------x m-----------e a----------- me-----------ssa-----------ge -----------I w-----------ill----------- be-----------