9.          What is the probability that the following project will take more than 10 weeks to complete if the activity means and standard deviations are as shown below?
Â
|
Activity |
Mean |
Standard Deviation |
|
1-2 |
5 |
1.3 |
|
2-3 |
4 |
1.0 |
|
1-3 |
8 |
1.6 |