16.            Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a mysterious New York lawyer (Mr. T). Relevant data are shown on the next page. The compli- cation is that Mr. T wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Note: No activity can be crashed more than two weeks.
CRASHING COSTS
|
 Activity |
Immediate Predecessor |
Normal Time (weeks) |
 1st Week |
 2nd Week |
|
K |
— |
9 |
$410 |
$415 |
|
L |
K |
7 |
125 |
— |
|
N |
K |
5 |
45 |
45 |
|
M |
L |
4 |
300 |
350 |
|
J |
N |
6 |
50 |
— |
|
Q |
J, M |
5 |
200 |
225 |
|
P |
Q |
8 |
— |
— |
|
Y |
Q |
7 |
85 |
90 |
|
Z |
P |
6 |
90 |
— |
|
End |
Y, Z |
 |
 |
 |
Develop a crashing schedule.