Zellars, Inc. is considering two mutually exclusive projects, A and B. Project A costs $95,000 and is expected to generate $65,000 in year one and $75,000 in year two. Project B costs $120,000 and is expected to generate $64,000 in year one, $67,000 in year two, $56,000 in year three, and $45,000 in year four. Zellars, Inc.'s required rate of return for these projects is 10%. The internal rate of return for Project B is (Points : 1) 29.74%. 30.79%. 35.27%. 36.77%
-----------