Michelle is the IT project manager for an implementation of seven new servers. The scope of the project is to install and configure a new network operating system for her organization. Three of the servers are to be located in the company headquarters in Atlanta. Two are to be installed in the Tampa office, and the remaining two are to be installed in the Nashville office.
The servers in Atlanta and Nashville have been installed successfully, but Jerry, the network administrator, has yet to install the servers in Tampa. Jerry reports that he is leery of moving from his current, stable environment to the new operating system the servers provide. Michelle, the project manager, insists that Jerry install the servers as planned to complete the project. A week passes and Jerry still has not completed the installation. What steps can Michelle take to ensure the installation is completed?
-----------