The following 5 overhaul jobs are waiting to be processed at Avianic’s Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Assume that all jobs arrived on day 180; today’s date is 200.

Using the critical ratio scheduling rule, in what sequence would the jobs be processed?