3.          Compute the multifactor productivity measure for each of the weeks shown for production of choc- olate bars. What do the productivity figures suggest? Assume 40-hour weeks and an hourly wage of
$12. Overhead is 1.5 times weekly labor cost. Material cost is $6 per pound.
|
Week |
Output (units) |
Workers |
Material (lbs) |
|
1 |
30,000 |
6 |
450 |
|
2 |
33,600 |
7 |
470 |
|
3 |
32,200 |
7 |
460 |
|
4 |
35,400 |
8 |
480 |
-----------