BE4-12 Spin Cycle Company uses three activity pools to apply overhead to its products. Each activity has a cost driver used to allocate the overhead costs to the product. The activities and related overhead costs are as follows: product design $40,000; machining
$300,000; and material handling $100,000. The cost drivers and expected use are as follows.
Expected Use of Cost Drivers
Activities Cost Drivers per Activity
|
Product design |
|
Number of product changes |
|
10 |
|
Machining |
|
Machine hours |
|
150,000 |
|
Material handling |
|
Number of setups |
|
100 |
(a) Compute the predetermined overhead rate for each activity. (b) Classify each of these activities as unit-level, batch-level, product-level, or facility-level.
-----------