BE4-12Â Spin Cycle Company uses three activity pools to apply overhead to its products. Each activity has a cost driver used to allocate the overhead costs to the product. The activities and related overhead costs are as follows: product design $40,000; machining
$300,000; and material handling $100,000. The cost drivers and expected use are as follows.
Expected Use of Cost Drivers
Activities                         Cost Drivers                                 per Activity
Â
|
Product design |
 |
Number of product changes |
 |
10 |
|
Machining |
 |
Machine hours |
 |
150,000 |
|
Material handling |
 |
Number of setups |
 |
100 |
(a)Â Compute the predetermined overhead rate for each activity. (b) Classify each of these activities as unit-level, batch-level, product-level, or facility-level.
-----------