P18-3 (Recognition of Profit and Entries on Long-Term Contract) On March 1, 2010, Chance Company entered into a contract to build an apartment building. It is estimated that the building will cost $2,000,000 and will take 3 years to complete. The contract price was $3,000,000. The following information pertains to the construction period:
2010 2011 2012
Costs to date: $600,000 $1,560,000 $2,100,000
Estimated costs to complete: 1,400,000 520,000 0
Progress billing to date: 1,050,000 2,000,000 3,000,000
Cash collected to date: 950,000 1,950,000 2,850,000
Instructions
(a) Compute the amount of gross profit to be recognized each year assuming the percentage-of-completion method is used.
(b) Prepare all necessary journal entries for 2012.
(c) Prepare a partial balance sheet for December 31, 2011, showing the balances in the receivables and inventory accounts.
Hel-----------lo -----------Sir-----------/Ma-----------dam----------- Â----------- -----------Tha-----------nk -----------You----------- fo-----------r u-----------sin-----------g o-----------ur -----------web-----------sit-----------e a-----------nd -----------acq-----------uis-----------iti-----------on -----------of -----------my -----------sol-----------uti-----------on.-----------Ple-----------ase----------- pi-----------ng -----------me -----------on -----------cha-----------t I----------- am----------- on-----------lin-----------e o-----------r i-----------nbo-----------x m-----------e a----------- me-----------ssa-----------ge -----------I w-----------ill----------- be----------- ca-----------tch-----------