Serenje Manufacturing Company produces nameplates and uses a job-order cost system. The following amounts relate to nameplate production for the month of June:
|
Work in process inventory, June 1 |
$620 |
|
Cost of materials directly assigned to production during June |
$1,800 |
|
Cost of labor directly assigned to production during June |
$1,200 |
|
Cost of nameplates completed during June |
$4,300 |
Serenje applies overhead at a predetermined overhead rate of 60% of direct material cost. At the end of June, only one job was in Work in Process inventory. This job had been charged with $150 of direct material cost. What is the direct labor cost assigned to this job?
A) $100
B) $160
C) $225
D) $530
Hel-----------lo -----------Sir-----------/Ma-----------dam-----------Tha-----------nk -----------You----------- fo-----------r u-----------sin-----------g o-----------ur -----------web-----------sit-----------e a-----------nd -----------and----------- ac-----------qui-----------sit-----------ion----------- of----------- my----------- po-----------ste-----------d s-----------olu-----------tio-----------n.P-----------lea-----------se -----------pin-----------g m-----------e o-----------n c-----------hat----------- I -----------am -----------onl-----------ine----------- or----------- in-----------box----------- me----------- a -----------mes-----------sag-----------e I----------- wi-----------ll